SHW on behalf of Cadogan Estates have just completed an External Repairs, Maintenance & Redecoration Works at 40 Lower Sloane Street, London, SW1W 8BP. The contract was to be completed within 12 weeks and the budget was £75,097.50 and came in £1,956.12 under budget.



The works consisted of the following:

 

  • Brickwork/Stone repairs & Cleaning

  • Roof Repairs

  • Rainwater good repairs

  • Window repairs

  • Decoration of previously painted items

  • Terra Cotta Brickwork repairs

 

William Kerr, Building Surveyor at SHW commented “We are most proud of the extensive terra cotta works to the first-floor balcony and triangular pediment which included taking a moulding of the existing tablet or ‘frieze’ and having it cast and then installed. This took about 4 months to produce as it is very specialist and finished by hand.”

 